THE SIOUX CITY COUNCIL REJECTED ALL EIGHT BIDS MONDAY FOR THE CONSTRUCTION OF A NEW POLICE DEPARTMENT STORAGE FACILITY AT THEIR TRAINING CENTER.
ALL OF THE BIDS WERE $100,000 TO $350,000 OVER THE ARCHITECT’S ESTIMATE.
POLICE CHIEF REX MUELLER TOLD THE COUNCIL THE PROJECT HAD SOME ADDITIONAL NEEDS THAT WEREN’T FIGURED INTO THAT ESTIMATE:
https://kscj.com/wp-content/uploads/2026/03/PDBLDG1.mp3
PDBLDG1 OC………LOT OF WORK. :25
THE CHIEF SAYS HE WOULD LIKE A CENTRAL LOCATION FOR A TRAINING CENTER, BUT ISN;T SURE IT SHOULD STILL BE NEAR THE AIRPORT:
https://kscj.com/wp-content/uploads/2026/03/PDBLDG2.mp3
PDBLDG2 OC……SOMEWHERE ELSE. :22
MUELLER SAYS WHEN THE TRAINING CENTER WAS ESTABLISHED OVER 25 YEARS AGO, IT INVOLVED REFURBISHING OLD BUILDINGS WHICH ARE NOW SHOWING THEIR AGE:
https://kscj.com/wp-content/uploads/2026/03/PDBLDG3.mp3
PDBLDG3 OC………….EXISTING FACILITIES. :25
CHIEF MUELLER SAYS THEY WILL DO SOME MORE STRATEGIC PLANNING AND CHECK WITH OTHER CITY DEPARTMENTS REGARDING EXISTING SPACE THEY MIGHT BE ABLE TO USE.
The post SC POLICE TRAINING CENTER UPGRADE PLACED ON HOLD appeared first on KSCJ 1360.